Application Summary


Office ID: 03 Application #: 119825 File #: 19-23
 
Project Name: Willowbrook Middle School
 
Project Scope: Alterations to 4-Bldgs. B, D, E, & P (A-2034, A03-103484), 1-Bldg. C (A-11672, A03-103484), 2-Bldgs. A & G (A-14037, A03-103484), 1-Bldg. H (A-2937, A03-103484), 2-Bldgs. J & T (A-5138, A03-103484), 2-Bldgs. K & O (A-29695, A03-103484), 1-Bldg. N (A-6837, A03-103484), 1-Bldg. L (A-11672, A03-118826), 1-Bldg. I (A-14037)
 
Address: 2601 N. Wilmington Avenue
 
City: Compton Zip: 90222    
 
PTN #: 73437-153 OPSC #:
 
Project Type: School (K-12) # Of Incr: 0
 
Project Class: Class 3 Special Type: NA
 
Estimated Amt: $500,000.00 Contracted Amt: $0.00
 
Construction Change Document Amt: $0.00 Final Project Cost: $0.00
 
Adj Est.Date#1: Adj Est.Amt#1: $0.00
 
Adj Est.Date#2: Adj Est.Amt#2: $0.00
 
Received Date: 5/1/2019 Approved Date: 10/7/2019
 
Approval Ext. Date: Closed Date:

Complete Submittal Received Date:

SB 575

Auto Fire Detection Sprinkler System
Required
Included In Plan

Required review services

Special review type

Energy Efficiency
0%
0%

Climate Zone: 0 Project's Sq.footage: 0 EPR Approved Date:
 
HPI: HPI Points: HPI Hours:
 
Energy Notes:
 
Client's Notes: SPOTC for submittal date of 05/01/19-(JG). 13 June 2019: Certify A03-119825 concurrently with A03-103484 to complete required unconstructed scope, scope cannot be reduced. Also, A03-119825 cannot be certified until A03-105694 and A03-107337 are certified (Araujo).