Office ID: 03 Application #: 114546 File #: 19-H28
 
Project Name: Canyon High School
 
Project Scope: Additions to 1-992 s.f. addition to existing Music classroom Bldg. Q (A03-27575 & 108498); Alterations to 1-Modernization of music classroom Bldg. Q; Construction of 1-New Auditorium (Bldg. U) and related site work.
 
Address: 19300 W. Nadal Street
 
City: Canyon Country Zip: 91351    
 
PTN #: 65136-61 OPSC #:
 
Project Type: School (K-12) # Of Incr: 0
 
Project Class: Class 1 Special Type: NA
 
Estimated Amt: $8,570,000.00 Contracted Amt: $13,939,977.00
 
Construction Change Document Amt: $1,502,223.00 Final Project Cost: $15,442,200.00
 
Adj Est.Date#1: Adj Est.Amt#1: $0.00
 
Adj Est.Date#2: Adj Est.Amt#2: $0.00
 
Received Date: 5/4/2012 Approved Date: 2/12/2013
 
Approval Ext. Date: Closed Date: 7/7/2017 1:51:22 PM

Complete Submittal Received Date: 6/29/2012

SB 575

Auto Fire Detection Sprinkler System
Required
Included In Plan

Required review services

Special review type

Energy Efficiency
0%
0%

Climate Zone: 0 Project's Sq.footage: 0 EPR Approved Date:
 
HPI: HPI Points: HPI Hours:
 
Energy Notes:
 
Client's Notes: DSA-1 incomp., access site plan incompl., pipe hanger conection missing, just lateral reisitance of the mezz at the open side in bldg. u. missing water flow test (6/4/12). Add. docs. received (6/29/12). 20 July 2012: SSS, FLS and ACS sent to Sacramento for plan check (Araujo).