Application Summary


Office ID: 03 Application #: 114337 File #: 19-41
 
Project Name: Lincoln Elementary School
 
Project Scope: Construction of 1-C.R. Bldg & Site Work
 
Address: 4310 New York Avenue
 
City: La Cresenta Zip: 91214    
 
PTN #: 64568-66 OPSC #:
 
Project Type: School (K-12) # Of Incr: 0
 
Project Class: Class 1 Special Type: NA
 
Estimated Amt: $1,776,840.00 Contracted Amt: $5,750,000.00
 
Construction Change Document Amt: $338,207.41 Final Project Cost: $0.00
 
Adj Est.Date#1: Adj Est.Amt#1: $0.00
 
Adj Est.Date#2: Adj Est.Amt#2: $0.00
 
Received Date: 1/12/2012 Approved Date: 6/27/2012
 
Approval Ext. Date: 6/27/2015 Closed Date: 6/5/2018 5:52:06 PM

Complete Submittal Received Date: 1/25/2012

SB 575

Auto Fire Detection Sprinkler System
Required
Included In Plan

Required review services

Special review type

Energy Efficiency
20.84%
0%

Climate Zone: 9 Project's Sq.footage: 0 EPR Approved Date: 5/30/2012
 
HPI: HPI Points: 33 HPI Hours: 3
 
Energy Notes: ***5/30/12 HPI verification for 35 Points under the 2010 HPI Regulations and the 2008 Energy Code. lb***3/29/13 Invoiced for $300 for 3 points that were not charged for originally: Reviewed 36 points and original payment was for 33 points. lb***
 
Client's Notes: Missing existing soil type info., missing seismic design parameters, incompl. RAM-Frame computer input/output, missing HVAC anchorage details,/calcs, incomple. AFSS submittal (1/18/12). Addn docs recvd 1/25/12. INCOMPLETE AFAS + AFSS SUBMITTED. NO FLS BACK CHECK UNTIL PR IS COMPLETED.***5/30/12 HPI verification for 35 Points under the 2010 HPI Regulations and the 2008 Energy Code. lb*** Rescheduled FLS backcheck : showed up 1 hr 15 min late on 6/12/12 CO! Request for extension of approval granted thru 6/27/2013. LC 1/22/14 Request for extension of approval granted thru 6/27/2014. LC 6/20/14