Application Summary


Office ID: 03 Application #: 110389 File #: 19-H1
 
Project Name: Mark Keppel High School - Phase 2
 
Project Scope: Construction of Science CR Bldg. B; Music/CR Bldg. C; Gym. Bldg.;(2)- Lunch Shelters; Trash Enclosure, and Site Works. Alteration to Admin/CR/Cafeteria/Aud./Lib. Bldg. A (A#s 104664, 106846)
 
Address: 501 E. Hellman Avenue
 
City: Alhambra Zip: 91801    
 
PTN #: 75713-34 OPSC #:
 
Project Type: School (K-12) # Of Incr: 0
 
Project Class: Class 1 Special Type: NA
 
Estimated Amt: $36,000,000.00 Contracted Amt: $38,058,410.00
 
Construction Change Document Amt: $2,812,294.52 Final Project Cost: $40,870,704.52
 
Adj Est.Date#1: Adj Est.Amt#1:
 
Adj Est.Date#2: Adj Est.Amt#2:
 
Received Date: 1/22/2007 Approved Date: 3/20/2008
 
Approval Ext. Date: Closed Date: 4/19/2016 12:24:35 PM

Complete Submittal Received Date: 2/21/2007

SB 575

Auto Fire Detection Sprinkler System
Required
Included In Plan

Required review services

Special review type

Energy Efficiency
%
%

Climate Zone: Project's Sq.footage: EPR Approved Date:
 
HPI: HPI Points: HPI Hours:
 
Energy Notes:
 
Client's Notes: Geotech report missing (01/30/07)...geotch report submitted (02/21/07)