Application Summary


Office ID: 03 Application #: 105216 File #: 19-66
 
Project Name: Mark Twain Elementary School
 
Project Scope: Construction of CONSTRUCTION OF TWO STORY UPPER GRADE BLDG.
 
Address: 12315 Thorson Ave.,
 
City: Lynwood Zip: 90262    
 
PTN #: N/A OPSC #:
 
Project Type: School (K-12) # Of Incr: 0
 
Project Class: Class 1 Special Type: NA
 
Estimated Amt: $6,200,000.00 Contracted Amt: $0.00
 
Construction Change Document Amt: $0.00 Final Project Cost: $0.00
 
Adj Est.Date#1: 12/20/2004 Adj Est.Amt#1: $7,671,319.00
 
Adj Est.Date#2: Adj Est.Amt#2: $0.00
 
Received Date: 7/16/2001 Approved Date: 7/29/2003
 
Approval Ext. Date: 6/18/2006 Closed Date: 4/21/2008

Complete Submittal Received Date:

SB 575

Auto Fire Detection Sprinkler System
Required
Included In Plan

Required review services

Special review type

Energy Efficiency
0%
0%

Climate Zone: 0 Project's Sq.footage: 0 EPR Approved Date:
 
HPI: HPI Points: HPI Hours:
 
Energy Notes:
 
Client's Notes: THE SIX (6) RELOCATABLE BILDGS. ARE NOT PART OF SCOPE OF WORK, PER LETTER FROM ARCHITECT. 08/15/01 NOT ABLE TO INPUTSTAUS WITH CCAREA3 CONSULTANT NAME FOR PLAN REVIEW COMPLETION 10/11/01 RVAUGHN.; 90 Day Letter 1/22/08; CLOSED W/O CERTIFICATION #3 4/21/08;